Warwick Farm Racecourse
Type
Mechanical Shed / MSB Upgrade / Fit-out
Client
MostynCopper
Duration
8 weeks
Completion
2021
Location
Warwick Farm, NSW
Project Overview
SCI Group served as principal contractor for the Main Switchboard (MSB) upgrade at Warwick Farm Racecourse. The existing MSB was deemed non-compliant and decommissioned, with a new switchboard chassis installed and upgraded busbars engineered to support increased amperage capacity. This complex electrical upgrade was delivered in a semi-live environment, requiring meticulous planning and coordination to ensure safety and minimal disruption to racecourse operations. In addition to the MSB works, SCI also delivered the new mechanics shed and staff facilities, further enhancing the functionality and infrastructure of the site.